A ladder stabiliser set on a weathered roof, gutter guard along the eave. Whether gutters are removed and rehung, and whether they are cleared of tear-off debris, are two separate scope lines that quotes routinely leave out. A Keys Roofing jobsite photograph.
The document

Ask Each Roofer How a Morning Fog Stop Gets Logged

A fog-delayed start is still a job-day event. Compare how each roofer decides to stop, who makes the call, and where the stop is written down.

Morning fog settles over low ground near the Mississippi and Missouri rivers and can sit on a roof well past the crew's scheduled start. Wet shingles, a damp deck and poor visibility over the eave are all reasons a foreman might hold the crew at the truck. Most homeowners never hear about the hold. The crew arrives, waits, and eventually either starts or does not. Each roofer you compare should be able to say how that morning gets decided, who makes the call, and where it is written down, because the answer tells you whether the day will show up on your record at all.

Why fog is a job-day question

Fog is not rain, so most roofing contracts handle it poorly. A rain plan usually names rain, snow or a lightning distance. Fog is left out, even though it can affect the work as much as a light drizzle does. Fog wets the surface overnight and burns off slowly on shaded north slopes and on the side of the house that faces a tree line. A crew that starts on schedule may be standing on a deck that looks dry from the street but still holds moisture under the granules.

Damp shingles are a concern for the seal. The sealant strip on an asphalt shingle needs a dry, warm surface to bond, and a shingle laid over moisture may not seal as it should. That is a workmanship question, and it belongs in the same conversation as the nailing and the starter course. A foreman who understands it will talk about the deck first and the clock second.

Visibility is the other half. On a two-story house the crew needs to see the eave, the ladder rails, the edge of the roof and each other. A low, thick fog can hide a ladder foot on wet grass or a worker on the far slope. A visibility stop is a safety call. It is separate from a weather stop, and a good roofer will name it separately in the log.

St. Louis springs and autumns produce these mornings often enough that a roofer who works here should have an answer ready. If the answer is a blank look, that is a comparison point in itself.

Roofer comparison

Put each roofer's answer on the same five points so you can see where they differ:

  • Who makes the call. Is it the foreman standing on site, the crew lead by phone, or the office? A call made by someone who can see the roof is different from a call made by someone who has only a forecast.
  • When the call is made. Some roofers set a fixed hour, such as the time the crew would normally leave the truck. Others decide once the foreman has walked the slope. Ask which one applies, and ask what the crew does while the decision is pending.
  • How you hear about it. The call should reach you the same morning, in writing if possible, with a sentence about what the crew is waiting on. A text that says the crew is delayed is not enough. A text that says the deck is wet on the north slope and the crew will start when it has dried is useful.
  • What the stop is called in the log. A day logged as a rain day, a visibility day and a deck-moisture day are three different entries. Ask each roofer what label the crew uses, and ask to see one past log entry with the label filled in.
  • Whether the day counts toward the schedule. Some roofers add the held day to the end of the job. Others compress the remaining steps. The difference changes the date on your calendar and the date your house sits open.

A roofer who answers all five points in plain terms is easier to hold to the answers later. A roofer who answers only the first point has left the other four for the morning of the job, which is the worst time to settle them.

What it costs

A held morning is still a morning the crew was booked for, and somebody has to pay for the hours. The bid should say which of three things happens. The first is that the hold is absorbed into the contract price and nothing extra is billed. The second is that the hold is billed as standby time at a stated rate. The third is that the hold is treated as a schedule change and the price stays the same while the date moves. None of these is wrong on its face, but each one shifts the cost to a different place.

Ask each roofer which of the three applies to a fog hold, and ask them to name the rate if standby is billed. A roofer who says standby is charged at the crew's day rate has given you a number you can check against the bid. A roofer who says it depends has not yet told you what it depends on.

Watch for the bid line that says weather days are included but does not define weather. If fog is not named, a roofer may treat it as a standby day, and you may find out only on the invoice. Ask for the definition in writing before you sign, and make sure the definition covers fog, damp decking and low visibility by name.

Keep the cost question separate from the safety question. A roofer who says the crew will stop because of fog is making a safety decision. A roofer who says the crew will bill standby for that stop is making a pricing decision. Both answers belong in the bid, and neither should depend on the other.

What to ask

  1. Does your contract name fog, and if so, is it a rain-plan item, a visibility item or a deck-moisture item?
  2. Who calls a fog stop on my roof, and what time is the call usually made?
  3. How will I hear about the stop, and will the message name the reason?
  4. What label does the crew log for a fog morning, and can I see a past entry?
  5. Does a fog-held day count against the schedule, and does it add to the price?
  6. If the deck is still damp after the fog lifts, what does the crew do with the rest of the morning?

Ask the same six questions of every roofer on your list, and write each answer next to the question it answers. The differences will be small on paper and large on the morning the fog sits on the roof. Keys Roofing answers questions like these at its office line, (314) 220-2333, and the answers can be put in writing before any deposit is paid.

Keys RoofingRoofing, gutters and downspouts · Greater St. Louis · Licensed and insured
The eleven items, in writing

Ask for the scope before you ask for the price

A document that names the underlayment, the flashing detail, the ventilation and the decking unit price can be laid beside another one and compared. A headline number on its own cannot.

Keys writes that document with photographs and measurements, and it is yours to keep whether or not the work goes to us. You are welcome to hand it to two other companies and ask them to price the same roof.

Keys Roofing, direct

Straight through to the Keys Roofing office. Roofing, gutters and downspouts across greater St. Louis, and nothing else.

(314) 220-2333

This goes to Keys Roofing, the company at number one. None of the other companies named on this site receive anything you type here.

Call (314) 220-2333Free inspection